Yeah i asked about that this morning..They have tapered the dirt around the building about 3ft out..They said even if there was no dirt all the way around the edge,that the slab is connected to the bottom board with bolts that are in the concrete all the way around..So basicly they put 4" bolts on the bottom board all the way around on the inside of the building before the pour started...But it looks good and the ground has runoff away from the building and everything looks as it should...
|